QESCO New Connection Process: Complete 2024 Guide

Step-by-step guide to apply for electricity connection in Balochistan via online portal or offline process

Document Requirements Online Application Connection Fees Troubleshooting
Apply Now

Are you looking to get a new electricity connection from QESCO (Quetta Electric Supply Company) in Balochistan? Whether you're a homeowner, business owner, or setting up a new property, understanding the QESCO new connection process is essential.

In this comprehensive guide, we'll walk you through:

  • Types of QESCO connections available
  • Required documents for application
  • Step-by-step application process (online & offline)
  • Connection fees and charges (2024 updated)
  • Common issues and troubleshooting tips

By the end, you'll know exactly how to get your QESCO electricity connection without delays. Let's get started!

1. Understanding QESCO (Quetta Electric Supply Company)

QESCO is responsible for electricity distribution in Balochistan, ensuring power supply to residential, commercial, and industrial consumers. If you need a new connection, you must follow QESCO's official process to avoid delays or rejections.

Types of QESCO Connections

Domestic (Residential)

For homes and apartments with standard load requirements

Commercial

For shops, offices, and small businesses

Industrial

For factories and manufacturing units

Agricultural

For tube wells and farming operations

Each connection type has different requirements, fees, and load capacities. Industrial connections typically require additional documentation and higher security deposits.

2. Documents Required for a New QESCO Connection

Before applying, gather these essential documents to ensure smooth processing of your application.

For Residential Connection

  • Copy of CNIC (applicant)
  • Proof of ownership (Property documents, lease agreement, or allotment letter)
  • Recent utility bill (if available)
  • NOC from the housing society (if applicable)

For Commercial/Industrial

  • CNIC of the business owner/partner
  • Business registration documents (if applicable)
  • Proof of property ownership or rent agreement
  • Site plan and load requirement details
  • Tax registration certificate (for industrial)

Note: Additional documents may be required based on your specific case. Contact QESCO office for exact requirements.

3. Step-by-Step QESCO New Connection Process

Option 1: Offline Application (In-Person Submission)

1

Visit the Nearest QESCO Office

Locate your nearest QESCO subdivision office. Bring all original documents for verification.

2

Obtain the Application Form

Request the new connection form (Form A-1) from the customer service counter.

3

Fill Out the Form

Provide accurate details including:

  • Applicant's full name and CNIC
  • Complete property address
  • Required load capacity (in kW)
  • Connection type (residential/commercial/industrial)
4

Attach Required Documents

Submit photocopies of all required documents along with the completed form. Keep originals for verification.

5

Pay the Connection Fee

Fees vary based on load and connection type (see section 4 below for current rates). Payment can be made via:

  • Bank draft in favor of QESCO
  • Cash deposit at designated bank counters
  • Online payment receipt (if paid in advance)
6

Inspection by QESCO Team

A QESCO team will visit your premises within 7-10 working days to:

  • Verify property details
  • Check wiring and electrical safety
  • Confirm load requirements
  • Determine meter placement
7

Meter Installation

Once approved, QESCO will install the meter and activate your connection within 3-5 working days after inspection.

Tip: Be present during installation to ensure proper setup and to receive your consumer number.

4. QESCO New Connection Fees & Charges (2024)

The cost of a new QESCO connection depends on the connection type and required load capacity. Below are the estimated fees for 2024:

Connection Type Load Capacity Estimated Fee (PKR) Processing Time
1-Phase Domestic Up to 5 kW 5,000 – 10,000 7-10 days
3-Phase Domestic 5-20 kW 15,000 – 30,000 10-15 days
Commercial 5-50 kW 20,000 – 50,000 10-20 days
Industrial (Small) 50-100 kW 50,000 – 100,000 15-25 days
Industrial (Large) 100+ kW 100,000+ 20-30 days
Agricultural Tube Well 25,000 – 50,000 10-20 days

Note: Fees may change based on government policies. Confirm exact charges with QESCO before applying. Additional costs may include wiring inspection charges and security deposits.

Payment Methods

Bank Draft
Cash Deposit
JazzCash/EasyPaisa
Credit/Debit Card

5. Common Issues & Troubleshooting

Delays in Processing

If your application is taking longer than expected:

  • Ensure all submitted documents are clear and valid
  • Follow up with QESCO via helpline 081-9202166
  • Visit the subdivision office with your reference number
  • Check if any additional information is required

Rejected Applications

Common reasons for rejection and solutions:

  • Incomplete documents: Resubmit with all required paperwork
  • Property ownership issues: Provide proper NOC from owner if renting
  • Incorrect information: Verify all details match your CNIC and property records
  • Unsafe wiring: Have a licensed electrician fix issues before reapplication

No Response After Submission

If you haven't received any updates:

  • Track status online using your reference number
  • Visit the QESCO office where you submitted your application
  • Escalate via QESCO complaints portal
  • Contact QESCO's customer service at 118 (from registered mobile)

QESCO Contact Information

Head Office:

QESCO Headquarters, Zarghoon Road, Quetta, Balochistan

Helpline:

081-9202166 (8AM-8PM)

Email:

info@qesco.com.pk

Complaints:

118 (from registered mobile)

6. FAQs About QESCO New Connection

Ready to Apply for Your QESCO Connection?

Follow our step-by-step guide to ensure a smooth application process and get your electricity connection without delays.